Schedule cache management tasks (Insight)

You can use Insight Cache Manager to schedule cache management to run during off-line hours.

  1. In the Cache Manager dialog box, use the Look In field to select the library and documents you want to include in your cache management task.

  2. In the Cache Management Tasks portion of the dialog box, select the processes to schedule, and then click Schedule.

  3. Log in on the User Name and Password dialog box.

    The user name you specify is used to run the task.

  4. In the Microsoft task schedule dialog box, schedule your task to run once, daily, weekly, monthly, or at startup or login.

    Your scheduled setting preferences are stored in CacheMgr.ini. This file is stored in the Solid Edge Program folder if you have Solid Edge loaded. The file is stored in the Insight Program folder if you have only stand-alone Insight Connect loaded.

    Tip:

    • If Solid Edge or Revision Manager is running when Cache Manager is scheduled to run, Cache Manager is cancelled and an error is added to the log file. To avoid this, make sure you close all files before leaving for the night.

    • You cannot have separate Cache Manager processes running simultaneously. If a process is still running when a second process is scheduled to run, the second process is cancelled and an error is added to the log file. To avoid this, make sure that you schedule sufficient time for each process to complete before another process begins.

    • If you are offline when a Cache Manager process is scheduled to run, Insight attempts to go back online and run the scheduled processes. Once the processes complete, you are returned to offline mode.

What are you looking for?
Look up more details